PML EAST · MEDLEY + MAIN · WEEKLY EOD REFRESH
How columns C–F on the Medley and Main tabs are rebuilt each week from the production schedule and material notes, and which files have to be uploaded to run it.
01
Upload all three every week. The tracker is the file being written; the other two are the sources it reads. Names carry a date or version number that changes weekly — match the current cycle.
G–J, in-file material notes K–L (Release Month + Weekly File Comments) when present, Manf Lot, and BF Code.C estimate, D category, E ship, F comment.AJ, Packaging Start AO, Packaging Finish AP, plus stage, BF Code, Release Month.K–L.02
Every source is matched to a tracker row on Manf Lot first, then order number as a fallback.
60E06 into scientific notation; both sides of every join are normalized so those still match.03
C, D and F are rebuilt fresh each week; E carries the prior week's commercial call.
| Column | Field | How it's set |
|---|---|---|
| C | estimate | Month of the fill-finish date for scheduled rows (e.g. September); <mon> ptnl for material-held rows; otherwise the prior estimate is carried. |
| D | category | Released for scheduled / clear items; otherwise the material category — Customer Supplied Material – Missing (No ETA / ETA Within 4 Weeks), PML Material – Missing, Pending MBR, Line Trial, or Customer Feedback Needed – Non Material. |
| E | Ship | Carried forward from the prior week — a commercial judgment that isn't in the schedules. |
| F | comment | Built fresh from the decision order in §4 and the templates in §5. |
04
Each written row is resolved by the first rule it matches, top to bottom.
DONE keeps it — even if its completed fill still shows on the historical schedule.newly released - not on schedule, category Released.Ship (E) carries forward in every case. Released status is confirmed against East Upcoming Releases. Anything already typed into C–F is kept, not overwritten.
05
Same wording as prior weeks. The delta note compares this week's fill-finish to last week's.
| Delta note | When |
|---|---|
(newly scheduled) | Prior week had no fill-finish date. |
(delayed v. last week finish M/D) | New fill date is later than last week's. |
(moved up v. last week finish M/D) | New fill date is earlier than last week's. |
| — none — | Fill date unchanged from last week. |
06
Read from the row's Status and its BF Code — the value Batch CMP/Closed means the bulk batch is complete.
| Condition | Reads as |
|---|---|
| Status = STD (Started) | batched already batched |
Status = RLS + BF Code Batch CMP/Closed | batched raw material clear + batch complete |
| Status = RLS + a real BF code | not yet batched raw material clear, not made |
| Status = NST (Not Started) | not yet batched never batched — even if a BF code shows CMP |
07
East-specific behaviours that shape the wording.
- on schedule; Main omits it.resleeve - fill finish M/D, not batched ….08
Things that change week to week or trip up a naive read.
XLOOKUP links that an offline recalc can't evaluate and would blank out. The file is saved as-is — only C–F change; Excel recomputes Totals and pivots on open.(newly scheduled).